All four new supporting columns installed at Worthing Pier
Worthing |
November 17, 2026

All four new supporting columns have now been installed at Worthing Pier as permanent repairs continue following storm damage that forced its closure in 2024.
Worthing Borough Council confirmed the progress on Thursday 12 November. The new columns are supported by 12-metre-long piles driven into the beach towards the southern end of the pier. They are designed to take the weight currently carried by a temporary steel support structure installed after the storm damage.
Contractor Mackley carried out overnight work to install the final column, including welding and encasing the bases in concrete. The council said the next stage will involve fitting brackets, tie bars and bull rails during the next set of spring tides later in November.